Ā· 27 min read
Can a permanent immersive exhibition pay its way?

You've found a building that would look incredible with the lights down. The creative team can already picture the rooms. Someone has calculated how many visitors could walk through each day, multiplied that by the ticket price, and produced a very attractive annual revenue figure.
Now you need to work out whether that figure describes a business you can actually run.
A permanent immersive exhibition needs enough paid visits to cover its running costs, keep the experience working and recover the money spent opening it within a period you can justify. Test those requirements against ordinary trading months, the admissions you can deliver and the lease you would be signing. A busy launch is encouraging. It doesn't answer the whole question.
The interesting part is that staying open for longer changes both sides of the calculation. You have more time to sell tickets, but you also keep paying for the building, people and equipment. The installation ages. The first wave of curious locals has already visited. Your next customer may cost more to reach.
This guide walks through that decision using a fictional exhibition. We'll build the operating budget, work out what each admission leaves, test the visitor forecast and connect the result to the opening investment. Then we'll look at what has to be true before you commit to the space.
Decide what permanent means for this exhibition
Start with the experience you intend to sell and how long you expect it to remain worth buying. A sequence of projection rooms, an interactive sound installation and a changing programme of digital artworks can all be described as immersive exhibitions. They don't necessarily have the same costs, visit length or reason to return.
Write a straightforward description of the paid visit. Explain what people encounter, how they move through it, how long they are likely to stay and what admission includes. If one room is the main attraction, be honest about that. It affects what happens when the room is unavailable and how much the rest of the visit can stand on its own.
Then define the intended commercial life. You might be proposing the same core installation for several years, a permanent venue with regularly commissioned work, or a long residency that could end without moving the entire business. Each version needs its own spending and sales forecast.
A changing programme can give previous visitors a reason to return, but somebody has to pay for that change. New artwork may require production, licensing, technical testing, publicity and a period when rooms are closed. Put those commitments into the plan before crediting the programme with repeat revenue.
The useful question is how long you can trade successfully in this location with this offer. The word permanent doesn't establish that. Neither does a long lease. A building can remain available after the audience has lost interest, and a popular installation can face a lease ending before its investment has been recovered.
Our event business plan template covers the wider company decision. For a permanent exhibition, develop the parts that continue after opening day, particularly the building commitment, equipment replacement and the demand for another month of admissions.
Price the complete opening project
Ask suppliers to quote the experience as it will operate for paying visitors. An equipment list is only one part of that. You also need the work that makes the equipment usable in your particular building and keeps the creative promise consistent across the visit.
Include design, content development, rights, hardware, installation, building alterations, power, ventilation, networking, acoustic treatment, access provision, signage and testing where they apply. Add professional fees, permissions, recruitment, staff training and launch spending. Record who supplies each item and which costs remain outside their quote.
The Welsh Government's exhibition costing toolkit, published in November 2025, is a useful prompt for reviewing scope. It distinguishes exhibition specifications and identifies design, content, copyright, lighting and interactive elements. Its indicative museum costs aren't a quote for your immersive attraction. Use current prices for your building and proposed work.
Suppose our fictional exhibition requires $420,000 to open. All money in the worked examples is USD, and every price, cost and attendance figure is invented for explanation. These aren't industry benchmarks, supplier estimates or Loopyah fees. The example assumes no sales-tax adjustment, no financing and no income tax; a real forecast must include the applicable amounts and payment dates.
The $420,000 consists of $90,000 for design and content, $140,000 for equipment, $110,000 for building work and pre-opening property costs, $30,000 for installation testing and training, $20,000 for launch activity, and $30,000 for identified uncertainties. Assume that entire amount is spent before opening. The categories have agreed boundaries, so installation work isn't charged again inside the hardware or building-work total. The property figure includes six months at $12,000 a month, leaving $38,000 for the assumed building work. Preparation pay is included in the design, testing and launch figures. All these payments are covered before the separate trading cash below is needed.
There is also a refundable $30,000 property deposit and $120,000 of opening cash available for trading. That makes the initial funding requirement $570,000. The deposit ties up money even though it isn't treated as a permanent opening expense in this example. Its eventual recovery remains conditional on the agreement and the condition of the premises.
Don't describe all $570,000 as the cost of the artwork, and don't forget the deposit because it might come back later. Show the spending, tied-up money and available trading cash separately. You'll need those distinctions when you test a late opening or decide how much money could actually be returned to the owners.
Agree how you will accept the finished installation
Before paying the final balance, agree how the supplier will demonstrate that the installation works as commissioned. A successful preview with the creative team isn't the same as a full operating day. You need to know whether the work can run for the intended hours, recover from ordinary faults and be handed over to your team.
Write the acceptance conditions into the agreement while the scope is being priced. Include the content and functions to be delivered, the testing period, the documents and access credentials you receive, and the training provided. State who signs off the work and what happens when something remains incomplete. Have the contract reviewed for your project rather than relying on a verbal promise to sort things out after launch.
The test should reflect the proposed visit. Run the complete sequence, allow visitors to pause and repeat interactions, and check the transition between rooms. Watch what staff actually have to do. If a host must restart an installation every few minutes, the labour forecast and the visitor promise both need attention.
Check recovery as well as normal operation. Ask the supplier to demonstrate the approved procedure following a power interruption, a failed player or a lost network connection where those failures are relevant. Your team needs a clear boundary between an ordinary restart and work that requires a qualified technician. Don't ask visitor staff to improvise technical repairs.
Documentation matters because the people who built the installation won't always be there. Record the supported equipment, configuration, content versions, backup arrangements and responsible contacts. Agree how replacements will be obtained and installed. If a particular component becomes unavailable, find out who will assess an alternative and what that work would cost.
Connect payment dates to the agreed delivery stages. A supplier may reasonably require money to order equipment, but you should understand how much remains payable if testing finds a problem. Also check when warranties and support periods begin. A long delay between equipment delivery and public opening could use part of that cover before the first paid visit.
Finally, preserve time to correct faults. If the installation is handed over immediately before a heavily promoted opening, you may have little practical room to test and repair it. Moving the opening can create extra payroll, rent and customer-service costs. Record that exposure in the dated cash forecast rather than treating commissioning as a free gap between construction and ticket revenue.
Understand the building commitment before choosing a payback period
Your lease needs to support the exhibition's operating plan. Check the permitted use, opening hours, installation access, alterations, noise conditions, repair duties and the process for obtaining necessary approvals. A low rent won't compensate for a building where the intended experience cannot operate as proposed.
Find out who pays when the roof leaks, the ventilation needs work or the electrical supply proves insufficient. Ask what happens to the improvements you've paid for when you leave. Some equipment may be removable, while a substantial part of the fit-out may have little value outside this particular building.
The exit matters just as much. For an England and Wales project, GOV.UK's guidance on ending a commercial property lease early explains that a break clause can have notice requirements and other conditions. Don't assume closing the exhibition ends the rent obligation. Have a solicitor check the actual lease and any guarantees; other jurisdictions have their own rules.
The example assumes a five-year lease, with the first six months used for building work and opening preparation. The rent for those months is already included in the opening budget. That leaves fifty-four months of intended trading inside the initial term. A payback calculation requiring nearly all fifty-four months leaves very little room for a slow start, a delayed approval or weak later demand.
You also need to understand when you can decide to leave. A possible break after several years may be useful, but its notice deadline could arrive before the proposed content refresh. Put both dates into the plan. Otherwise you may commission expensive new work while missing the chance to end an unsuitable property commitment.
Check removal and reinstatement costs with the same care as installation. Keep them as an explicit end-of-term cash requirement, with any likely equipment resale shown separately. Don't assume the incoming tenant wants your rooms or that a resale estimate will be realised on the day you need the money.
The lease should be one of the inputs to your investment decision. It shouldn't be a fixed assumption that forces the rest of the forecast to become more optimistic.
Build a monthly budget that includes the people doing the work
A permanent exhibition has bills when the rooms are quiet. Build the monthly budget from the opening calendar and staffing arrangement you intend to use. Include opening and closing work, supervision, visitor support, cleaning, technical checks, management and the work of selling the next month's visits.
Pay the owner for a defined job if the owner will work in the business. Leaving that work unpaid can make the attraction appear viable while it depends on someone providing months of free management. If the owner also invests money, the wage for their work and the return on their investment are separate questions.
For our fictional exhibition, monthly operating costs are $48,000 before costs attached to individual paid visitors. That includes $12,000 for rent and property charges, $20,000 for fully costed staffing including owner management, $4,000 for utilities, $4,000 for routine technical support and maintenance, $5,000 for marketing, and $3,000 for insurance and administration.
The budget includes the planned opening pattern and the ordinary level of work needed to run it. We assume these costs stay unchanged across the attendance scenarios below. If a busier month requires another shift, additional security or longer opening hours, add that cost before using the same calculation.
Now set aside a further $4,000 per month for future equipment replacement and planned renewal. This is a cash planning allowance, held back rather than distributed. It is separate from the routine maintenance already included in the $48,000, and it doesn't establish the accounting expense for depreciation or future asset purchases.
Together, the operating bills and renewal allowance require $52,000 per month before anything is available to recover the original opening investment. The distinction matters. You can cover today's invoices while gradually losing the ability to maintain the experience people paid to see.
Look beyond the first year too. If the lease includes rent reviews or a supplier's support agreement renews at a different price, use those future costs in the relevant months. A single repeated monthly budget is useful for understanding the example. It isn't a substitute for a forecast over your actual commitment.
Work out what each paid admission leaves
The headline ticket price isn't the amount available to pay the building's bills. Forecast the average amount you retain after discounts and refunds, then subtract the costs that arise with the paid visit. Keep the definitions consistent so the same charge isn't deducted twice.
Our example retains an average $30 of ticket revenue per paid admission after discounts and refunds, before selling costs. Assume there are no additional unrecovered refund charges, complimentary admissions or other income in this simplified model. Free allocations and their service costs would need to be added to a real plan.
Each paid visit then costs $6. That consists of an invented $2 selling charge, $1 of visitor consumables and $3 of content royalty. The selling charge is a teaching assumption. The royalty is a flat amount for each paid admission under this fictional agreement. Different rights agreements can produce very different costs.
That leaves $24 per paid visit to cover the monthly budget. In financial terms this is the admission's contribution, meaning the money remaining after those visitor-related costs. At 2,000 paid visits, the exhibition generates $48,000 of contribution, exactly enough to cover the operating bills and nothing towards the renewal allowance.
At 2,500 paid visits, contribution is $60,000. Subtract $48,000 of operating bills and the $4,000 renewal allowance, and $8,000 remains. At 3,000 visits, the amount remaining after both is $20,000. These are different attendance assumptions for the same monthly offer and cost structure, not measured results from a real attraction.
The US Small Business Administration's planning guidance and break-even calculation explains the basic relationship between fixed costs, price and variable cost. Applied here, covering $52,000 requires 2,167 paid visits at $24 each, rounded up to a whole admission. That clears this monthly cash hurdle by $8. It still doesn't recover the opening investment.
Our event break-even guide covers adjustments for mixed ticket prices and other revenue. Use those adjustments when they apply, while keeping this exhibition's long-term investment requirement visible.
Recover the installation cost within a believable trading life
Now return to the $420,000 spent opening the exhibition. If the attraction consistently leaves $8,000 per month after operating bills and the renewal allowance, simple recovery takes fifty-two and a half trading months. At $20,000 per month, it takes twenty-one.
Those are deliberately simple payback calculations. They assume the stated result starts immediately and continues unchanged, with no financing, tax, additional capital spending or value placed on receiving money earlier. They exclude recovery of the separate deposit and any additional trading cash consumed. They also provide no extra return to reward the owners for risking their money.
Even with those favourable simplifications, the lower case nearly uses all fifty-four trading months available in our lease example. That's a reason to investigate the assumptions before signing. It isn't evidence that the investment has comfortably passed.
If you want the initial $420,000 recovered within thirty-six trading months, the exhibition needs to leave about $11,667 per month after its operating bills and renewal allowance. Add that requirement to $52,000, then divide by the $24 contribution per admission. Rounded up, the result is 2,653 paid visits per month.
At 2,653 paid visits, the contribution is $63,672. After the $52,000 monthly requirement, $11,672 remains. Over thirty-six identical months, that totals $420,192. This is a useful check on the arithmetic, with the same limitations as the simple payback calculation. Actual monthly cash movements and changing costs still need to be modelled.
You might decide a longer recovery period is acceptable. You might require a shorter period and an additional return. Make that choice explicit with the people providing the money. The answer will depend on their funding terms, the commercial life of the content, the lease and the alternatives available to them.
For a substantial investment, have your accountant or finance adviser assess the dated cash forecast and appropriate investment measures. Simple payback helps explain the decision, but it ignores too much to approve a long property commitment on its own. Don't describe the $8,000 or $20,000 figures as accounting profit; they are the amounts left under the specific cash planning assumptions above.
Calculate admissions the experience can actually deliver
Before asking whether 2,653 monthly paid visits is achievable, establish how many visits you can sell without damaging the experience or exceeding the assessed limits. The number has to come from the proposed route, staffing, operating hours and site assessment.
A room full of people isn't necessarily a room in which everyone receives the visit you advertised. Visitors may pause at a popular installation, wait for an interaction or spend longer in the final room. A steady admission pattern at the entrance can still produce a queue inside.
Suppose testing and the necessary assessments support an illustrative plan of twenty visitor departures each trading day, with sixteen paid places per departure. The exhibition opens twenty-five days in the model month. That produces 8,000 paid places before any additional closures or allocations. These are invented planning figures, not safety limits or a recommended group size.
Under that plan, 2,500 paid visits use 31.25% of monthly paid inventory. The 2,653 visits needed for the simplified thirty-six-month recovery use about 33.2%. Those percentages can look reassuring, but they're averages across every saleable place. Your buyers may mostly want the same Saturday afternoons.
If eight weekend days offer 320 places each, they provide 2,560 places. Filling every one of them still leaves ninety-three paid visits to find elsewhere to reach 2,653. More realistically, some weekend places may also remain unsold. A monthly percentage doesn't tell you which times people will book.
Test the visit under the proposed arrival pattern, including late arrivals, access needs, cleaning and staff breaks. Count people already inside, those waiting to enter and accompanying visitors under the relevant limits. Confirm the capacity and emergency arrangements with qualified people for the site. Ticket quantities should follow that work.
Use a calendar with actual opening days when preparing the real forecast. Allow for maintenance, public holidays, private use, content changes and other closures. Don't call every hour the building could theoretically open a selling hour. You still need a team and a worthwhile experience during it.
Forecast who comes after the opening audience
A launch can bring press coverage, invited guests, creators and people who already follow the artist. Keep that audience separate from the customers you expect to acquire during ordinary trading. You need to understand which part can continue and what you must spend to reach it.
Build the forecast around recognisable buyers. Local adults choosing a weekend activity may behave differently from tourists, school groups or families visiting during holidays. Explain why each group would choose this exhibition, when they could visit and how they would discover the offer.
Don't start with the population of the city and choose a convenient percentage. Start with evidence you can examine. That might include a paid test, comparable results from your own previous work, bookings from a distribution partner or enquiries that have progressed to a specific priced offer. Keep uncertain prospects separate from confirmed bookings.
Our guide to researching event demand in a new city explains how to test the audience and offer. For this decision, include quieter periods in the research. If the permanent venue will depend on weekday sales, a sold-out Saturday prototype leaves that part of the plan unresolved.
For repeat visits, name what changes. A person bringing a friend is different from someone buying another visit to see new work. A membership may bring cash upfront, but it can also replace future full-price purchases and occupy popular times. Forecast the income and visits under the actual terms you intend to offer.
Avoid counting the same person twice as both a new tourist sale and a returning local customer. You don't need perfect knowledge of future visitors. You do need a forecast whose categories make sense and whose weak assumptions are visible enough to test.
If a distributor proposes bringing groups, ask for the actual commercial arrangement. Establish the price you retain, who controls dates, when payment arrives and how cancellations work. A partner saying they can introduce schools isn't the same as schools booking visits. Include only the level of business your evidence supports, with the rest shown as a possibility.
You can test some of this before committing to a permanent venue. A limited paid residency can reveal what buyers understood, which times they chose and how the visit worked. It will have its own costs and may benefit from urgency that a permanent attraction won't have. Record those differences instead of copying its opening sales into every future month.
Keep a simple record of what the test actually answered. Did people pay the proposed price? Did they buy without a personal invitation? Did weekdays attract the intended audience? What did it cost to reach those buyers? A test that leaves one question unresolved can still be useful, provided you don't treat it as proof of the entire business.
The money spent attracting buyers needs similar care. If the $5,000 monthly marketing budget is expected to support 2,500 paid visits, explain which sales come through that spending and which come through other routes. A quiet month may require more promotion, while discounted offers may reduce the amount retained per visitor. Test those changes together.
Treat maintenance and refreshes as part of the offer
An immersive installation has to keep delivering its advertised experience. A dark projector, drifting audio or unreliable interaction can remove the part people came to see. Decide which faults require closure, which allow a reduced experience and who has authority to make that call.
Ask suppliers for an operating and support plan before accepting the build. You need to know what staff can check, what needs specialist attention, what spares are available and how long replacement could take. Record the conditions of any warranty and what the support agreement actually covers.
HSE's work equipment maintenance guidance, for Great Britain, emphasises planned maintenance, reporting faults and using people competent for the work. It also addresses making maintenance safe for workers and others nearby. Have your technical team translate the applicable requirements and manufacturers' instructions into the arrangements for your installation.
Financially, separate routine servicing from major replacement and creative renewal. Routine support might keep an existing room functioning. Replacing a failed system might restore it. A new commission changes what visitors can see. Combining everything under maintenance can hide the actual commitments and make the renewal allowance hard to judge.
In our model, the $4,000 monthly allowance builds $48,000 over a year if nothing is withdrawn. Suppose a planned renewal requires $60,000 at the end of that year. The allowance alone is $12,000 short, before considering any other use of the fund. You need extra funding, a different timing or an agreed change in scope.
Also model the closure. If work removes three trading days that would otherwise have sold 100 paid visits each, the exhibition loses 300 visits and $7,200 of contribution at the assumed $24 per visit. Fixed monthly bills stay unchanged in this separate scenario. The $60,000 renewal invoice and the lost contribution are different effects.
Don't deduct the same renewal invoice twice when preparing the full cash forecast. The allowance shows money reserved for the future payment. When the payment occurs, reduce that reserved cash and record any additional funding needed. Your accountant can advise how the expenditure is treated in the accounts.
Make the rights agreement last as long as the business plan
Check what you are entitled to show, adapt, promote and maintain. Paying someone to create content doesn't by itself explain every right your business receives. The exhibition may combine original work, music, recorded performance, software and material licensed from other owners.
WIPO's copyright guidance identifies protected works including films, music, artistic works and computer programs, and describes rights such as public performance and reproduction. The permissions your exhibition needs depend on the works, uses and jurisdiction. Have the relevant agreements reviewed for the actual project.
For the commercial plan, identify the licensed venue, territory, duration, permitted audience uses and any renewal conditions. Ask what happens if you move buildings, change equipment or need a replacement contractor to maintain the experience. Where access to project files or software is needed, agree that access rather than assuming it will be provided later.
A licence that ends before you expect to recover the opening investment deserves attention. You might be able to renew it, but the renewal price or permission may be uncertain. Use the period you have actually secured in the main forecast and keep the possible extension visible as a separate assumption.
Read the payment definitions carefully. A percentage of gross ticket sales produces a different result from the same percentage after specified deductions. Minimum guarantees can keep a payment high during weak months. The example's flat $3 royalty per paid visit is deliberately simple; replace it with the actual contract calculation.
Agree reporting, payment dates and how refunds, concessions, free visits and bundled offers are treated. If a new ticket type changes the royalty calculation, somebody needs to know before it goes on sale. These details affect the amount left per admission, so they belong in the pricing work.
Test a weak first year and the cash it consumes
Now put a slow start into the example. Suppose the first three trading months each attract 1,500 paid visits. The next nine each attract 2,500. Keep the same $24 contribution, $48,000 operating bills and $4,000 monthly renewal allowance, with no additional income or cost changes.
Each of the first three months generates $36,000 of contribution. After $48,000 of operating bills, it loses $12,000 of operating cash. Transferring another $4,000 into the renewal fund reduces freely available trading cash by $16,000. Across those months, that is $48,000 less available trading cash, including $12,000 moved into the renewal fund.
Each later month leaves $8,000 after bills and the allowance. Nine such months add $72,000, so the year increases freely available trading cash by $24,000 overall. Total contribution is $648,000 from 27,000 paid visits, less $576,000 of operating bills and $48,000 reserved for renewal.
For this first-year test, assume renewal takes place outside the stated trading days. The separate three-day closure loss above is not included. The $24,000 increase is much less than twelve months at the later attendance level would suggest. It also hasn't recovered the original $420,000. If a $60,000 renewal payment then falls due, the reserved $48,000 leaves another $12,000 to fund. Under these assumptions, just $12,000 of the year's increase in freely available cash remains after meeting that shortfall.
The Australian Government's cash-flow management guide recommends tracking money in and out and updating the statement for seasonal patterns and payment dates. Build your forecast that way. The monthly example above explains the trading result; it doesn't establish when actual ticket payouts, payroll or supplier balances reach the bank.
Our event cash-flow forecast guide helps you put payments on dates. Start before opening, include delays, and continue through the lease's relevant decision points. Keep money needed for refunds and other obligations identified. Selling future visits brings delivery commitments as well as receipts.
For this example, the separate $120,000 opening trading fund provides room to absorb the early reductions in available cash. It isn't a recommended reserve. Check the greatest dated shortfall in your own forecast and how it will be funded, including any restrictions on the money you intend to use.
Set ticket prices without asking every visitor to pay the maximum
Immersive exhibition pricing starts with the visit people are willing to buy. Your required average receipt tells you what the proposed business needs, but it doesn't prove the audience will pay that amount. If the price and likely demand don't support the budget, revise the proposal before committing more money.
Test a clear offer with the total price, visit expectations, available dates and any restrictions. Explain features that affect the buying decision, such as flashing effects, sound intensity, stairs, seating opportunities or a route that requires sustained standing. Check the details with the people responsible for access and the installation.
Use an expected mix of tickets in the forecast. Standard admission, concessions and group bookings may each leave a different amount. Keep the sales quantities consistent with the audience forecast and include any additional service or selling costs for those bookings. A large group enquiry is useful only if the visit and price can actually be delivered.
Here's a separate sensitivity using the same 2,500 monthly paid visits. If discounts reduce the retained average ticket receipt by $3 while the $6 visitor cost stays unchanged, contribution falls to $21 per visit. Total contribution becomes $52,500. Just $500 remains after the $52,000 monthly requirement, compared with $8,000 under the original assumption.
A discount could still be worthwhile if it brings enough additional demand at acceptable costs. At $21 contribution, you need 2,858 visits to leave at least the original $8,000 after the same $52,000 requirement. That's 358 more paid visits than the original case, rounded to whole admissions. Check where those people would come from and when they would visit.
Loopyah's ticket selling tools let you set ticket types and releases with their own prices and quantities, and show buyers the current price and sold-out options. Use the agreed offer to configure the tickets. You still need to decide whether the resulting sales mix supports this exhibition and whether the release quantities fit the assessed operating plan.
Keep the price test distinct from your long-term forecast. One successful opening offer doesn't establish that the same visitors will return at a higher price. Review what sold, who bought and what you retained before expanding availability or introducing a new concession.
Write the decision before signing the next commitment
Bring the evidence together in a short approval note. It should explain what the exhibition sells, who is expected to buy, what the opening project costs and what happens during weak trading. Attach the dated financial forecast and the quotes behind it so someone can challenge the assumptions.
State the investment condition in ordinary words. For example, the fictional project needs evidence supporting at least 2,653 monthly paid visits at the original price and cost assumptions to meet its simplified thirty-six-month recovery target. That is a calculated requirement, not a sales forecast. The research must explain whether it is believable.
Record the unresolved items that could change the decision. These might include permission for the intended use, a confirmed electrical upgrade price, the final rights term or demand during quieter months. Assign someone to resolve each item before the relevant payment becomes unavoidable. Don't approve an installation quote while silently assuming every unresolved building cost will be small.
Use clear decision dates during trading too. Review retained ticket income, visitor-related costs, payroll, faults, available cash and renewal spending against the plan. If attendance is below the required level, identify a specific action and its cost, then update the forecast. More advertising may help, but it also needs paying for.
Before a major refresh or lease extension, assess the next period using the money and obligations still ahead. Money already spent cannot be recovered by simply staying open longer. The next commitment needs its own case, including the cost of closing and any obligations that continue either way.
If the exhibition only works with full weekends, strong weekday sales, an unchanged installation and no meaningful delays, keep testing or change the proposal. A smaller first installation, a better property agreement or a limited paid residency may produce evidence at a commitment you can afford. Choose the version whose likely paid visits can support the experience, the people running it and the money required to keep it open.